Schedule for Feb. 21-Mar. 2

Audrain County
Construction:
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; job has not been scheduled; estimated completion: summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; job has not been scheduled. estimated completion: summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; job has not been scheduled; estimated completion: summer 2012
Maintenance:
Routes E, C – cleaning out around box culverts
Various Routes – filling potholes, driveway and approach repairs, drainage and culvert repairs

Pike County
Construction:
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; preconstruction conference 2/21/2012; estimated completion: summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: summer 2012
Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville; bridge to close March 19, 2012 for 52 days with detour over Routes WW, D and H; estimated completion: May 2012
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; job has not been scheduled; estimated completion: summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn.; to be scheduled after May 2012; estimated completion: summer 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; to be scheduled after May 2012; estimated completion: summer 2012
Route H – Seal coat from Route W south junction to MO 79; ;to be scheduled after May 2012; estimated completion: summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; job has not been scheduled; estimated completion: summer 2012
Maintenance:
Route D – Feb. 21 ditch work and shoulder repair work two miles south of Route 79 junction
Route 79 – Feb. 21-24 shoulder repair work in various locations
Routes UU, 61 & HH Junction – culvert repairs
Route NN – Feb. 22 – Mar. 2 culvert repairs
Various Routes – Feb. 21-24 cutting brush; traffic reduced to one lane
Various Routes – pothole patching and other road repairs