MoDot Weekly Report

Posted on Wednesday, April 30, 2014 at 1:36 pm

MoDOTSchedule for April 28 – May 9, 2014
Audrain County
Construction
US 54 – Inactive; Surface improvements at various locations, eastbound lanes scheduled for diamond grinding operations June 16-28 and westbound June 29- July 3; Estimated Completion: Fall 2014
US 54 – Inactive; Resurface from route J in Mexico to MO 19 south junction near Martinsburg (Scotts Corner); Estimated Completion: Fall 2014
MO 15 – Inactive; Sealing operations from MO 154 to just north of MO 22; Estimated Completion: Fall 2014
Route Z – Inactive; Bridge improvements/redeck at Young’s Creek located 2 miles north of Route ZZ near Mexico; Estimated Completion: Fall 2014
Route T – Inactive Bridge improvements/redeck at Young’s Creek located 3.7 miles east of Route C near Centralia; Estimated Completion: Fall 2014
Maintenance
Various Routes – Possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations

Pike County
Construction
US 61 – Surface improvements at various locations; diamond grinding operations scheduled in northbound lanes from May 26 – June 14 and in southbound lanes from April 27 – May 24; Estimated Completion: Fall 2014
US 54- Inactive; Surface improvements at various locations; diamond grinding operations scheduled in eastbound lanes June 16-28 and westbound lanes June 29 – July 3; Estimated Completion: Fall 2014
US 54 – Inactive; Steel grid deck and joint repair on Champ Clark Bridge; Estimated Completion: Fall 2014
Maintenance
Various Routes – Possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations
Ralls County
Construction
US 61 – Surface improvements at various locations; diamond grinding operations scheduled in northbound lanes from May 26- June 14, and in southbound lanes from April 27 – May 24; Estimated Completion: Fall 2014
Route A – Bridge deck replacement on Turkey Creek Bridge; Road closed at the bridge up to 38 days; final clean up and deck sealing. Tentative opening April 30. Detour over MO 19, and Routes H and A
Route A – Inactive; Bridge deck replacement on Ely Creek Bridge; Road to be closed at the bridge up to 37 days; tentatively scheduled to April 30. Detour over MO 19, Routes EE, H and A. Estimated Completion: early June 2014
Route B – Inactive; Bridge replacement at Hurley Branch located 2.5 miles south of MO 154 near Perry; road to be closed at the bridge
Route B – Inactive; Bridge replacement at Lick Creek located 2.9 miles south of MO 154 near Perry; road to be closed at the bridge
Route EE – Inactive; Sealing operations from Route J to MO 19; Estimated Completion: Fall 2014
Route J – Inactive; Sealing operations from US 36 near Monroe City to MO 154 at Perry; Estimated Completion: Fall 2014
Route W – Inactive; Sealing operations from US 24 to Route J; Estimated Completion: Fall 2014

Maintenance
Various Routes – Possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.