Audrain County
Construction
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; not active; estimated completion: Summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; not active; estimated completion: Summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; not active; estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012
Maintenance
Various Routes – June 25-28 ditch work and spraying for weed control; no traffic interruptions
Pike County
Construction
Route D – ROAD CLOSED for Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet; detour over MO 79 and Routes N, W and WW; 80% complete; contractor will work on curb and asphalt; Estimated completion: June 29, 2012
US 54 – ROAD CLOSED for Safe and Sound Bridge Replacement at Noix Creek between Bowling Green and Louisiana – Commercial Vehicle Detour Recommended: US 54, MO 79 south, Route B west, US 61 North or South; Local and Tourism Detour Recommended: US 54, Route UU, US 61 North or South; 8% complete; contractor working on end bents and intermediate bents; Estimated completion: August 7, 2012
US 54 – Safe and Sound Bridge Replacement at Noix Creek between Bowling Green and Louisiana – Bridge to close June 25, 2012 for 40 days; Commercial Vehicle Detour Recommended: US 54, MO 79 south, Route B west, US 61 North or South; Local and Tourism Detour Recommended: US 54, Route UU, US 61 North or South
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; project scheduled to begin June 5-12; estimated completion: Summer 2012
Route H – Seal coat from Route W south junction to MO 79; project scheduled to begin June 4; one lane traffic in the work zone; estimated completion: Summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; scheduled to begin at a later date; one lane traffic during working hours; estimated completion: July 2012
Maintenance
Route H – June 25 one lane traffic from 7:30 a.m. to 2 p.m. for pavement repairs at various locations from Route W at Paynesville to Route D at Eolia
Route WW – June 25 one lane traffic from 2 p.m. to 4 p.m. for pavement repairs at various locations from Route D to Route W near Paynesville
Route F – June 26 one lane traffic from 7 a.m. to 4 p.m. for pavement repairs at various locations from US 61 to the end of State Maintenance
Route HH – June 27-28 one lane traffic from 7 a.m. to 4 p.m. for pavement repairs at various locations from US 61 to Route Z in Lincoln County
Route Y – June 25-28 one lane traffic from 7 a.m. to 4 p.m. for ditch work at various locations from Business 54 at Bowling Green west to Route M
US 61 – July 2-6 sign maintenance and repairs at various locations from the IA State line south into Lincoln Co.; shoulder work with little to no impact to traffic