MoDOT Weekly Report

Posted on Wednesday, May 16, 2012 at 9:10 am

Schedule for May 14-25

Audrain County
Construction
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill tentatively scheduled to begin in June; estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012
Maintenance
Major Routes – May 14 begin mowing major routes
Minor Routes – May 21 begin mowing minor routes
Various Routes – pothole patching, culvert and ditch work with no lane closures.