Schedule for April 30-May 11
Audrain County
Construction
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill tentatively scheduled to begin in June; estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012
Maintenance
Route FF – culvert replacements, shoulder work only; possible short-term one lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – bridge deck repair, drainage work, shoulder repair, spraying roadsides for weed control and sign work; possible short-term one lane traffic with cautionary signs and flaggers at the work zone.

Pike County
Construction
Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville with detour over Routes WW, D and H; 75% complete; contractor working on barrier curb and water proofing; estimated completion: May 14, 2012
Route D – Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet – Bridge to close May 7, 2012 for 58 days with detour over MO 79 and Routes N, W and WW; estimated completion: June 27, 2012
US 54 Champ Clark Bridge – Bridge repair on bridge over Mississippi River at Louisiana; BRIDGE CLOSED Friday, April 27 at 6 p.m. through Saturday, May 5 at 6 for repairs; estimated completion: May 2012; contractor – Halverson Const.
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; one lane traffic beginning May 1; estimated completion: Summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: Summer 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; project scheduled to begin June 6; estimated completion: Summer 2012
Route H – Seal coat from Route W south junction to MO 79; project scheduled to begin June 12; estimated completion: Summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; scheduled to begin in June; one lane traffic during working hours; estimated completion: Summer 2012
Maintenance
Route NN – April 30-May 4 drainage work at culverts; one lane traffic at various locations from 8 a.m. to 3 p.m. each day.

Ralls County
Construction
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012.
Route T – Resurface from just south of MO 79 to Route N south of Hannibal; contractor tentatively plans to begin work June 1, 2012; estimated completion: Summer 2012
MO 154 – Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route E – Seal coat from MO 79 to end of State maintenance near Saverton; job will not be scheduled until after May 2012; estimated completion: Summer 2012
Route T – Seal coat from Route N south of Hannibal to MO 79 near Ashburn; tentative start date June 1; estimated completion: Summer 2012
Route V – Seal coat from Ralls Street in New London to Route T; job will not be scheduled until after May 2012; estimated completion: Summer 2012
Route N – Seal coat from Route T to MO 79 near Saverton; job will not be scheduled until after May 2012; estimated completion: Summer 2012
Maintenance
Route T – May 3 road closed from 8 a.m. to 3:30 p.m. to replace 4 culverts located between Scotts Lane and Whitaker Lane south of Hannibal; alternate routes must be used during this time; some areas of the road will be open to local residential traffic only.
Route T – May 4 road closed from 8 a.m. to 1 p.m. to replace 1 culvert located almost 3 miles south of Route V junction between Caribou Drive and Barnard Road; alternate routes must be used during this time; some areas of the road will be open to local residential traffic only.
Routes J & H – shoulder repairs; moving operation with intermittent one lane traffic.
Routes H, CC & 79 – grade and repair county road entrances and driveway approaches; possible short-term one lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – pavement repair, spraying roadsides for weed control and sign work; possible short-term one lane traffic with cautionary signs and flaggers at the work zone.