Schedule for April 23-May 4
Audrain County
Construction:
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; tentatively scheduled to begin in June; estimated completion: Summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill tentatively scheduled to begin in June; estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012
Maintenance: Route FF – April 23-27 culvert replacements just west of Mexico; traffic reduced to one lane
Route J – April 23-27 culvert replacements 1.5 mile west of Route B; cautionary signs in place
Various Routes – April 23- May 4 bridge deck repair, drainage work, shoulder repair spraying roadsides for weed control and sign work
Pike County
Construction: Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville; 60% complete; contractor will be setting beams and grouting; detour over Routes WW, D and H; estimated completion: May 14, 2012
Route D – Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet – Bridge to close May 7, 2012 for 58 days with detour over MO 79 and Routes N, W and WW; estimated completion: June 27, 2012
US 54 Champ Clark Bridge – Bridge repair on bridge over Mississippi River at Louisiana; 1% complete; April 23 – April 27- 10 foot width restriction from approximately 9:00 a.m. until 3:00 – 4:00 p.m. each day; Friday, April 27, 6:00 p.m., through Friday, May 4, 6:00 p.m., BRIDGE CLOSED for repairs; estimated completion: May 2012; contractor – Halverson Const.
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; one lane traffic beginning May 1; estimated completion: Summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: Summer 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; project scheduled to begin June 6; estimated completion: Summer 2012
Route H – Seal coat from Route W south junction to MO 79; project scheduled to begin June 12; estimated completion: Summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; scheduled to begin in June; one lane traffic during working hours; estimated completion: Summer 20122
Maintenance: Routes 161, 54, WW & C – April 23- May 4 pavement repair; traffic reduced to one lane
Route NN – April 23 road closed from 8 a.m. to 3 p.m. for culvert replacement located 3.5 miles east of US 61 just north of Co. Rd. 255; alternate routes must be used during this time.
Route H – April 23 hot mix patching from MO 79 at Annada to Route W at Paynesville; one lane traffic from 7 a.m. to 3:30 p.m.
Route D – April 23-27 spraying for weed control, moving operation with intermittent one lane traffic and blocker truck at the work zone.
Various Routes – April 23- May 4 pavement repair, spraying roadsides for weed control and sign work