Schedule for Mar. 26-April 6
Audrain County
Construction:
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; preconstruction conference scheduled for March 28, 2012; estimated completion: Summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; preconstruction conference scheduled for March 28, 2012; estimated completion: Summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; preconstruction conference scheduled for March 28, 2012; estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012
Maintenance:
Route 54 East – culvert replacements in various locations; traffic reduced to one lane
Route J – adding rock around bridge piers; traffic reduced to one lane

Pike County
Construction:
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; one lane traffic beginning May 1; estimated completion: Summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: Summer 2012
Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville – Bridge to close March 26 at 8:00 a.m. for 52 days with detour over Routes WW, D and H; estimated completion: May 14, 2012
Route D – Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet – Bridge to close April 30, 2012 for 58 days with detour over MO 79 and Routes N, W and WW; estimated completion: June 27, 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; to be scheduled after May 2012; estimated completion: Summer 2012
Route H – Seal coat from Route W south junction to MO 79; ;to be scheduled after May 2012; estimated completion: Summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; job has not been scheduled; estimated completion: Summer 2012
US 54 Champ Clark Bridge – Bridge repair on bridge over Mississippi River at Louisiana; contractor will be taking measurements on the bridge Tuesday, March 27 with a 10-foot restriction from 9:00 a.m.-2:00 p.m.; April 23 – April 27- 10 foot width restriction from approximately 9:00 a.m. until 3:00 – 4:00 p.m. each day; Friday, April 27, 6:00 p.m., through Friday, May 4, 6:00 p.m., BRIDGE CLOSED for repairs; estimated completion: May 2012; contractor – Halverson Const.
Maintenance:
MO 79 – Mar. 26-27 bridge deck repairs at Big Calumet Creek; traffic reduced to one lane with flaggers from 8 a.m. to 4 p.m.
Route 79 – March 26-30 sweeping shoulders between Louisiana and Clarksville
Route 54 – March 26-30 washing Champ Clark Bridge deck at Louisiana
Route NN – April 1-6 routine culvert work in various locations with possible intermittent lane closures

Ralls County
Construction:
Route T – Resurface from just south of MO 79 to Route N south of Hannibal; contractor tentatively plans to begin work June 1, 2012; estimated completion: Summer 2012
MO 154 – Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia; preconstruction conference scheduled for March 28, 2012; estimated completion: Summer 2012
Route E – Seal coat from MO 79 to end of State maintenance near Saverton; job will not be scheduled until after May 2012; estimated completion: Summer 2012
Route T – Seal coat from Route N south of Hannibal to MO 79 near Ashburn; job will not be scheduled until after May 2012; estimated completion: Summer 2012
Route V – Seal coat from Ralls Street in New London to Route T; job will not be scheduled until after May 2012; estimated completion: Summer 2012
Route N – Seal coat from Route T to MO 79 near Saverton; job will not be scheduled until after May 2012; estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: Summer 2012.
Maintenance:
Route 61 – March 26-30 grading outer roads, and repairing shoulders, county road entrances and driveway approaches
Route 79 – March 26-30 slide repair ¾ mile south of Routes N and E; traffic reduced to one lane
Routes J & H – shoulder repairs, moving operation with cautionary signs and trucks
Route O – culvert work in various locations, traffic reduced to one lane with flagmen, 7:30a.m. – 3:00p.m.
Routes T, N, 79 – March 26-30 grade and repair county road entrances and driveway approaches
Routes H & CC – April 2-6 grade and repair county road entrances and driveway approaches
Routes 19/154 – April 2-6 concrete replacement at junction east of Perry; traffic reduced to one lane 7:00a.m. – 4:00p.m.