Schedule for Mar. 19-30
Audrain County
Construction:
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; preconstruction conference scheduled for March 28, 2012; estimated completion: summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; preconstruction conference scheduled for March 28, 2012; estimated completion: summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; preconstruction conference scheduled for March 28, 2012; estimated completion: summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion summer 2012
Maintenance:
Routes 54 East & J – culvert replacements; traffic reduced to one lane
Various Routes – filling potholes, drainage work, edge rut repair, cutting brush and washing bridges
Pike County
Construction:
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; project inactive – one lane traffic beginning May 1; estimated completion: summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: summer 2012
Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville – Bridge to close March 26 at 8:00 a.m. for 52 days with detour over Routes WW, D and H; estimated completion May 14, 2012
Route D – Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet – Bridge to close April 30, 2012 for 58 days with detour over MO 79 and Routes N, W and WW; estimated completion June 27, 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; to be scheduled after May 2012; estimated completion: summer 2012
Route H – Seal coat from Route W south junction to MO 79; ;to be scheduled after May 2012; estimated completion: summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; job has not been scheduled; estimated completion: summer 2012
US 54 Champ Clark Bridge – Bridge repair on bridge over Mississippi River at Louisiana; traffic reduced to one lane Friday, March 9 with 10 foot lane restriction; April 23 – April 27- 10 foot width restriction from approximately 9:00 a.m. until 3:00 – 4:00 p.m. each day; Friday, April 27, 6:00 p.m., through Friday, May 4, 6:00 p.m., BRIDGE CLOSED for repairs; estimated completion May 2012; contractor – Halverson Const.
Maintenance:
Route 79 – March 19-20 cleaning bridge decks at Big Calumet Creek; traffic reduced to one lane
MO 79 – Mar. 26-27 bridge deck repairs at Big Calumet Creek; traffic reduced to one lane with flaggers from 8 a.m. to 4 p.m.
Various Routes – washing bridges, culvert repairs and pothole patching