MoDOT Weekly Report

Posted on Tuesday, March 13, 2012 at 10:02 pm

Schedule for Mar. 12-23
Audrain County
Construction:
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; job has not been scheduled; estimated completion: summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; job has not been scheduled. estimated completion: summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; job has not been scheduled; estimated completion: summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion summer 2012
Pike County
Construction: Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; preconstruction conference 2/21/2012; estimated completion: summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: summer 2012
Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville – Bridge to close March 26, 2012 for 52 days with detour over Routes WW, D and H; estimated completion May 14, 2012
Route D – Safe and Sound Bridge replacement at Little Calumet Creek just south of Route N near Calumet – Bridge to close April 30, 2012 for 58 days with detour over MO 79 and Routes N, W and WW; estimated completion June 27, 2012
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; contractor tentatively plans to begin work May 1, 2012; estimated completion: summer 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; to be scheduled after May 2012; estimated completion: summer 2012
Route H – Seal coat from Route W south junction to MO 79; ;to be scheduled after May 2012; estimated completion: summer 2012
US 54 Champ Clark Bridge – Bridge repair on bridge over Mississippi River at Louisiana; traffic reduced to one lane Friday, March 9 with 10 foot lane restriction; April 23 – April 27- 10 foot width restriction from approximately 9:00 a.m. until 3:00 – 4:00 p.m. each day; Friday, April 27, 6:00 p.m., through Friday, May 4, 6:00 p.m., BRIDGE CLOSED for repairs; estimated completion May 2012; contractor – Halverson Const.
Maintenance: MO 79 – Mar.  19-20 bridge deck repairs at Big Calumet Creek; traffic reduced to one lane with flaggers from 8 a.m. to 4 p.m.
US 54 – sealing cracks between Louisiana and Bowling Green; one lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – filling potholes, removing brush and trees, sign repairs, driveway and approach work, drainage and culvert repairs, and shoulder work; one lane closed with signs and flaggers at work zones.
Ralls County
Construction:
Route T – Resurface from just south of MO 79 to Route N south of Hannibal; contractor tentatively plans to begin work June 1, 2012; estimated completion: summer 2012
MO 154 – Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia; job has not been scheduled; estimated completion: summer 2012
Route E – Seal coat from MO 79 to end of State maintenance near Saverton; job will not be scheduled until after May 2012; estimated completion: summer 2012
Route T – Seal coat from Route N south of Hannibal to MO 79 near Ashburn; job will not be scheduled until after May 2012; estimated completion: summer 2012
Route V – Seal coat from Ralls Street in New London to Route T; job will not be scheduled until after May 2012; estimated completion: summer 2012
Route N – Seal coat from Route T to MO 79 near Saverton; job will not be scheduled until after May 2012; estimated completion: summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: summer 2012.
Maintenance:
US 61 northbound – bridge work at Bear Creek Bridge just south of Hannibal; one lane traffic with cautionary truck at the work zone.
Various Routes – filling potholes, moving operation with short-term one lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – sign repairs and replacements, one lane closed with signs and flaggers at the work zone.
Randolph County
Construction
Route B – Resurfacing from Route A to US 63 near Clark, 8.541 miles. Project has not been scheduled; estimated completion October 2012; contractor – APAC-Missouri, Inc.
Route M – Resurfacing from US 63 in Moberly to MO 151 at the Monroe county line, 10.869 miles. Project has not been scheduled; estimated completion October 2012; contractor – APAC-Missouri, Inc.
MO 3 – Resurfacing from Route T to north of US 24 near Clifton Hill, 12.721 miles. Project has not been scheduled; estimated completion October 2012; contractor – APAC-Missouri, Inc.
Maintenance:
Various Routes – filling potholes, moving operation with short-term one lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – cutting and removing brush, one lane closed with signs and flaggers at the work zone.
Various Routes – sign repairs and replacements, one lane closed with signs and flaggers at the work zone.
Various Routes – driveway and approach work on shoulders at various location, cautionary signs and flaggers at the work zones.
Various Routes – drainage and culvert work; short-term one-lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – shoulder work at various locations, short term one lane traffic with cautionary signs and flaggers at the work zone.
Schuyler County
Maintenance:
Various Routes – washing bridges, filling potholes, and edgerut and shoulder repairs, moving operation with short-term one lane traffic with cautionary signs and flaggers at the work zone.
Scotland County
Maintenance:
Various Routes – washing bridges, filling potholes, and edgerut and shoulder repairs, moving operation with short-term one lane traffic with cautionary signs and flaggers at the work zone.
Shelby County
Construction:
Route DD – Safe and Sound Bridge replacement at Otter Creek west of Maud – Bridge to close March 13 at 8 a.m. for 48 days with detour over Route TT, US 36 and MO 151; estimated completion April 29, 2012
Route BB – Safe and Sound Bridge replacement at Garnett Branch between Epworth and Plevna – Bridge to close April 2, 2012 for 48 days with detour over MO 15 and Route M; estimated completion May 17, 2012
Route H – Safe and Sound Bridge replacement at Hilton Branch south of Leonard – Bridge to close April 30, 2012 for 39 days with detour over MO 151 and Route K; estimated completion June 8, 2012
Maintenance:
Route O – March 12 road closed from 8:30 a.m. to 3 p.m. for culvert pipe replacement between Beck and Kirchoff Roads; alternate routes should be used during this time.
Route Z – March 14 road closed from 8:30 a.m. to 2 p.m. for culvert replacement approximately ½ mile north of US 36 at Hunnewell; alternate routes should be used during this time.
Routes M, 151, MM, DD, TT, V – cutting and removing brush, one lane closed with signs and flaggers at the work zone.
Various Routes – filling potholes, moving operation with short-term one lane traffic with cautionary signs and flaggers at the work zone.
Various Routes – sign repairs and replacements, one lane closed with signs and flaggers at the work zone.
Warren County
Construction:
I-70 eastbound – Resurface driving lanes and shoulders from the St. Charles Co. line to Wright City; tentative start date – April 16; estimated completion: summer 2012
Route MM – Resurface from Old 40 to Route M at Warrenton; job not scheduled; estimated completion: summer 2012
Route AA – Resurface from Route 47 to the end of state maintenance; job not scheduled; estimated completion: summer 2012
Route A – Safe and Sound Bridge replacement at Camp Creek east of Truxton – Bridge to close April 7, 2012 for 52 days with detour over MO 47 and Routes W and A; estimated completion May 29, 2012
MO 94 – Seal coat from MO 19 to Route T at Augusta near the Warren/St. Charles Co. line; 32.67 miles; project has not been scheduled; estimated completion October 2012; contractor – Bross Construction
Maintenance:
Route 94 – March 9-12 bridge deck repairs at Loutre Slough; one lane traffic with signs and flaggers at the work zone from 8 a.m. to 4 p.m.
Route Y – March 13-14 bridge deck repairs at Bear Creek; one lane traffic with signs and flaggers at the work zone from 8 a.m. to 4 p.m.
Route J – Mar. 15-16 bridge deck repairs at Coon Creek; traffic reduced to one lane with flaggers from 8 a.m. to 4 p.m.
Various Routes – washing bridge structure and decks, one-lane traffic with protective truck and signs at the work zones.
Various Routes – filling potholes, removing brush and trees, sign repairs, driveway and approach work, drainage and culvert repairs, and shoulder work; one lane closed with signs and flaggers at the work zone.

————————————————————————

To view information about MoDOT visit http://www.modot.org