MoDOT Weekly Report

Posted on Wednesday, February 29, 2012 at 1:11 am

Schedule for Feb. 27-Mar. 9
Audrain County
Construction:
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; job has not been scheduled; estimated completion: summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; job has not been scheduled. estimated completion: summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; job has not been scheduled; estimated completion: summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion summer 2012
Maintenance:
Various Routes – dragline work
Various Routes – cutting brush, filling potholes, drainage work and edge rut repair

Pike County
Construction:
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; preconstruction conference 2/21/2012; estimated completion: summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; job will not be scheduled until after May 2012;l estimated completion: summer 2012
Route W – Safe and Sound Bridge replacement at Ramsey Creek just north of Paynesville; bridge to close March 19, 2012 for 52 days with detour over Routes WW, D and H; estimated completion: May 2012
Route UU – Resurface from US 61 near Bowling Green to US 54 near Louisiana; contractor tentatively plans to begin work May 1, 2012; estimated completion: summer 2012
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn.; to be scheduled after May 2012; estimated completion: summer 2012
Route Z – Seal coat from Route 161 to US 61 in Pike and Lincoln Counties; to be scheduled after May 2012; estimated completion: summer 2012
Route H – Seal coat from Route W south junction to MO 79; ;to be scheduled after May 2012; estimated completion: summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; job has not been scheduled; estimated completion: summer 2012
Maintenance:
Route NN – culvert work; possible intermittent lane closures
Route 79 – Feb. 27- March 2 shoulder repairs in various locations
Route W – Feb. – March 2 edge rut repair in various locations; traffic reduced to one lane
Route 54 – filling cracks; traffic reduced to one lane
Various Routes – pothole patching and other road repairs
Various Routes – hot pouring bridge joints
Ralls County
Construction:
Route T – Resurface from just south of MO 79 to Route N south of Hannibal; contractor tentatively plans to begin work June 1, 2012; estimated completion: summer 2012
MO 154 – Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia; job has not been scheduled; estimated completion: summer 2012
Route E – Seal coat from MO 79 to end of State maintenance near Saverton; job will not be scheduled until after May 2012; estimated completion: summer 2012
Route T – Seal coat from Route N south of Hannibal to MO 79 near Ashburn; job will not be scheduled until after May 2012; estimated completion: summer 2012
Route V – Seal coat from Ralls Street in New London to Route T; job will not be scheduled until after May 2012; estimated completion: summer 2012
Route N – Seal coat from Route T to MO 79 near Saverton; job will not be scheduled until after May 2012; estimated completion: summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J, 27 miles; job has not been scheduled; estimated completion: summer 2012.
Maintenance:
Route 154 – culvert work; traffic reduced to one lane
Route 154 – March 1, road closed for culvert replacement, just east of Route P; 7:30 a.m. – 3:30 p.m.
Routes T – grade and repair driveway entrances and mailbox approaches; shoulder repair
Route 61 – grade outer roads and repair county road entrances and driveway approaches; shoulder repair
Various Routes – pothole patching and cutting brush; traffic reduced to one lane