MoDOT Weekly Report

Schedule for June 3-14

Audrain County
Maintenance
MO 19 РJune 11 one lane traffic SB at W. Fork Quivre River Bridge between CR 424 and 416  for approach work
Various Routes -June 3-14 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Montgomery County
Construction
MO 161 – Resurfacing from Route M to MO 19 north junction in Montgomery City, 17.75 miles; 0% complete – Project inactive, Work tentatively scheduled to begin mid-July; one lane traffic with pilot car in use while work is performed; Estimated Completion: Summer 2013; Troy Project Office
Maintenance
Route FF – June 3-4 one lane traffic 7 a.m. to 5 p.m. for pavement repairs from Route E to New Truxton Road
Route E – June 5-6 one lane traffic 7 a.m. to 5 p.m. for pavement repairs from Route DD to Route CC
Route E – June 10-11 one lane traffic 7 a.m. to 5 p.m. for pavement repairs from Route CC to Route O
Route CC – June 12 one lane traffic 7 a.m. to 5 p.m. for pavement repairs from Route E to MO 161
Various Routes -June 3-14 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Pike County
Construction
MO 79 – Bridge replacement over Little Calumet Creek; 0% complete – Project inactive, tentatively scheduled for 6/24-8/16; Estimated Completion: Fall 2013; Troy Project Office
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 95% complete- semi final inspection pending; Estimated Completion: Summer 2013; Hannibal Project Office
Maintenance
Various Routes -June 3-14 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Ralls County
Construction
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 95% complete- semi final inspection pending; Estimated Completion: Summer 2013; Hannibal Project Office
MO 79 – Pavement and shoulder improvements from Third Street Overpass in Marion County to Route E and N junction near Saverton; 0% complete – Project inactive, schedule pending; lane and road closures coordinated in intervals at various locations during construction. Motorists urged to use alternate routes, some areas of the road open to local residential traffic only. Estimated Completion: Fall 2013; Hannibal Project Office
Route J – Preventative maintenance on Mark Twain Lake bridges over the Cannon Reservoir and Lick Creek. Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail. Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work. Full bridge closures will not take place between Memorial and Labor Day due to tourism and recreational use of the lake. 0% complete – Project inactive, schedule pending; Estimated Completion: Fall 2013; Macon Project Office
Maintenance
Various Routes -June 3-14 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Posted on Wednesday, June 5, 2013 at 1:24 pm