MoDOT Weekly Report

Schedule for May 28 – June 7

Audrain County
Maintenance
Various Routes -May 28-June 7 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Montgomery County
Construction
MO 161 – Resurfacing from Route M to MO 19 north junction in Montgomery City, 17.75 miles; 0% complete – Project inactive, Work tentatively scheduled to begin mid-July; one lane traffic with pilot car in use while work is performed; Estimated Completion: Summer 2013; Troy Project Office

Maintenance
MO 161 – May 29 bridge deck sealing at the Elkhorn Creek Bridge with one lane traffic from 8 a.m. to 9 a.m. from Meadowlark Road to Golden Rod Road near Buell.
MO 161 – May 29 bridge deck sealing at the Cuivre River Bridge with one lane traffic from 9 a.m. to 10 a.m. from Route AC to Route T just north of Middletown.
Route FF – June 3 one lane traffic from 7 a.m. to 5 p.m. for patching at various locations from New Truxton Road at the beginning of State Maintenance to Route E.
Route E – June 4 one lane traffic from 7 a.m. to 5 p.m. for patching at various locations from Route NN at I-70 to Meadowlark Road at Route O near Olney.
Route JJ – June 5 one lane traffic from 7 a.m. to 5 p.m. for patching at various locations from Route F to Route E.
Various Routes -May 28-June 7 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Pike County
Construction
MO 79 – Bridge replacement over Little Calumet Creek; 0% complete – Project inactive, tentatively scheduled for 6/24-8/16.
Estimated Completion: Fall 2013; Troy Project Office
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 95% complete- striping and final clean up; Estimated Completion: Summer 2013; Hannibal Project Office

Maintenance
Various Routes -May 28-June 7 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Ralls County
Construction
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 95% complete- striping and final clean up; Estimated Completion: Summer 2013; Hannibal Project Office
MO 79 – Pavement and shoulder improvements from Third Street Overpass in Marion County to Route E and N junction near Saverton; 0% complete – Project inactive, schedule pending; lane and road closures coordinated in intervals at various locations during construction. Motorists urged to use alternate routes, some areas of the road open to local residential traffic only. Estimated Completion: Fall 2013; Hannibal Project Office
Route J – Preventative maintenance on Mark Twain Lake bridges over the Cannon Reservoir and Lick Creek.
Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail.
Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work.
Full bridge closures will not take place between Memorial and Labor Day due to tourism and recreational use of the lake. 0% complete – Project inactive, schedule pending;
Estimated Completion: Fall 2013; Macon Project Office

Maintenance
Route DD – May 23 road closed from 7 a.m. to 3 p.m. from Sweet Bay Lane near Central Stone to the end of pavement at Sheil and Huntington Lane and Sydney Road intersection for culvert replacement.
Various Routes -May 28-June 7 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Posted on Wednesday, May 29, 2013 at 1:42 pm