MoDOT Weekly Report

Posted on Wednesday, May 22, 2013 at 8:32 am

—May 20-31

Audrain County
Maintenance
Route B – May 23 road closed 8 a.m. – 2 p.m. from Route J to Route D in Ralls County for culvert replacement
Various Routes -May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Pike County
Construction
MO 79 – Bridge replacement over Little Calumet Creek; 0% complete – Project inactive, tentatively scheduled for 6/24-8/16; Estimated Completion: Fall 2013; Troy Project Office
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 75% complete- rumblestrip and striping NB and SB lanes; Estimated Completion: Summer 2013; Hannibal Project Office
Maintenance
Various Routes -May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Ralls County
Construction
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 75% complete- rumblestrip and  striping NB and SB lanes; Estimated Completion: Summer 2013; Hannibal Project Office
MO 79 – Pavement and shoulder improvements from Third Street Overpass in Marion County to Route E and N junction near Saverton; 0% complete – Project inactive, schedule pending; lane and road closures coordinated in intervals at various locations during construction. Motorists urged to use alternate routes, some areas of the road open to local residential traffic only. Estimated Completion: Fall 2013; Hannibal Project Office
Route J – Preventative maintenance on Mark Twain Lake bridges over the Cannon Reservoir and Lick Creek. Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail.
Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work. Full bridge closures will not take place between Memorial and Labor Day due to tourism and recreational use of the lake. 0% complete – Project inactive, schedule pending; Estimated Completion: Fall 2013; Macon Project Office
Maintenance
Route DD – May 23 road closed from 7 a.m. to 3 p.m. from Sweet Bay Lane near Central Stone to the end of pavement at Sheil and Huntington Lane and Sydney Road intersection for culvert replacement.
Various Routes -May 20-31 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.