MoDOT Maintenance

Schedule for April 15-26, 2013
Audrain County
Maintenance
MO 15/22 (Muldrow Street) – April 15-19 one lane traffic with 10 ft. width restriction 7 a.m. – 4 p.m. between Promenade and Quisenberry Streets in Mexico for pavement repair
Various Routes – April 15-26 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Pike County
Construction
MO 79 – Bridge replacement over Little Calumet Creek; 0% complete – Project inactive, schedule pending; Estimated Completion: Fall 2013; Troy Project Office
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 15% complete- asphalt operations in NB and SB lane, one lane traffic through work zone; Estimated Completion: Summer 2013; Hannibal Project Office
Maintenance
US 54 – April 15-16 one lane traffic with 10 ft. width restriction from 8 a.m. to 3 p.m. for bridge maintenance on the Champ Clark Bridge over the Mississippi River at Louisiana.
Route M – April 22 one lane traffic from 8 a.m. to 3 p.m. for shoulder work approximately 5 miles south of US 54.
Various Routes – April 15-26 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Ralls County
Construction
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 15% complete- asphalt operations in NB and SB lane, one lane traffic through work zone; Estimated Completion: Summer 2013; Hannibal Project Office
MO 79 – Pavement and shoulder improvements from Third Street Overpass in Marion County to Route E and N junction near Saverton; 0% complete – Project inactive, schedule pending; work could begin as early as May. Lane and road closures coordinated in intervals at various locations during construction. Motorists urged to use alternate routes, some areas of the road open to local residential traffic only. Estimated Completion: Fall 2013; Hannibal Project Office
Route J – Preventative maintenance on Mark Twain Lake bridges over the Cannon Reservoir and Lick Creek. Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail. Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work. Full bridge closures will not take place between Memorial and Labor Day due to tourism and recreational use of the lake. 0% complete – Project inactive, schedule pending; Estimated Completion: Fall 2013; Macon Project Office
Maintenance
Route EE – April 17 one lane traffic from 8 a.m. to 2 p.m. with Truman Lane closed at EE for a culvert replacement.
Various Routes – April 15-26 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Posted on Wednesday, April 17, 2013 at 12:11 pm