MoDOT Maintenance

—Schedule for April 8-19, 2013

Audrain County
Maintenance
Various Routes – April 8-19 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Montgomery County
Construction
MO 161 – Resurfacing from Route M to MO 19 north junction in Montgomery City, 17.75 miles; 0% complete – Project inactive, schedule pending; Estimated Completion: Summer 2013; Troy Project Office
Maintenance
MO 161 – April 15-16 closed from 7:30 a.m. to 5 p.m. for bridge deck repairs at the Elkhorn Creek Bridge between Route CC and V near Buell, and the Cuivre River Bridge located between Middletown and Route T.
MO 161 – April 17-19 closed 7:30 a.m. to 5 p.m. for bridge deck repairs at the Cuivre River Bridge located between Middletown and Route T.
Route EE – April 8-9 road closed 8 a.m. to 3 p.m. from MO 94 to Warden Branch Road to replace three culverts; some areas of the road will be open to local traffic only.
Various Routes – April 8-19 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Pike County
Construction
MO 79 – Bridge replacement over Little Calumet Creek; 0% complete – Project inactive, schedule pending; Estimated Completion: Fall 2013; Troy Project Office
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 5% complete- asphalt operations in SB lane, one lane traffic through work zone; Estimated Completion: Summer 2013; Hannibal Project Office
Maintenance
Various Routes – April 8-19 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Ralls County
Construction
US 61 – Rehabilitate pavement on northbound and southbound lanes from just south of New London to just south of Route UU at Bowling Green, 11.92 miles Project 5% complete- asphalt operations in SB lane, one lane traffic through work zone; Estimated Completion: Summer 2013; Hannibal Project Office
MO 79 – Pavement and shoulder improvements from Third Street Overpass in Marion County to Route E and N junction near Saverton; 0% complete – Project inactive, schedule pending; work could begin as early as May. Lane and road closures coordinated in intervals at various locations during construction. Motorists urged to use alternate routes, some areas of the road open to local residential traffic only. Estimated Completion: Fall 2013; Hannibal Project Office
Route J – Preventative maintenance on Mark Twain Lake bridges over the Cannon Reservoir and Lick Creek. Work involves substructure repairs and modifications, expansion joint replacement, removal and replacement of asphalt surface and upgrading the existing guardrail. Each bridge will be closed for 20-30 days once the structural work begins with some lane closures for surface work. Full bridge closures will not take place between Memorial and Labor Day due to tourism and recreational use of the lake. 0% complete – Project inactive, schedule pending; Estimated Completion: Fall 2013; Macon Project Office
Maintenance
US 61 – Sunday, April 7, 10-10:30 a.m. intermittent traffic stops with delays of up to 15 minutes north and southbound just south of Warren Barrett Drive in Hannibal for installation of fiber optic cable by Ralls County Electric and Universal Cable Services crews
Various Routes – April 8-19 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.

Posted on Wednesday, April 10, 2013 at 6:53 am