MoDOT Weekly Report

—Schedule for August 6-17, 2012
Audrain County
Construction
Route JJ – Resurface from US 54 at Mexico to the end of state maintenance; inactive ; Estimated completion: Summer 2012
Route B – Resurface from US 54 through Rush Hill to Route J; inactive; Estimated completion: Summer 2012
Route KK – Resurface from MO 19 at Laddonia to Route B north of Rush Hill; inactive; Estimated completion: Summer 2012
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J; scheduled to begin Aug. 6; contractor will be performing coldmilling operations for bonded concrete intersection at Rte. 19 & Rte. H/P in Center; Estimated completion: Summer 2012
Maintenance
Route C – Aug. 6 ROAD CLOSED 7 a.m. 12 p.m. from Rte. 151 to Monroe County line from for pavement repairs
Route 54 – Aug. 6-9 one lane traffic 7 a.m. to 3:30 p.m. from Rte. 154 to Bus. 54  for milling operations
Route CC – Aug. 6-7 ROAD CLOSED 7 a.m. 4 p.m. from Rte. C to Rte. 15 for pavement repairs
Various Routes – Aug. 6-17 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations

Pike County
Construction
US 54 – OPEN TO TRAFFIC at Noix Creek between Bowling Green and Louisiana
US 54 – ROAD CLOSED for Safe and Sound Bridge Replacement at Noix Creek between Bowling Green and Louisiana -Recommended Commercial Vehicle Detour – US 54, MO 79 south, Route B west, US 61 North or South; Recommended Local and Tourism Detour – US 54, Route UU, US 61 North or South;98% complete; tentatively plan to open late Saturday by 9 p.m. if site conditions permit
MO 79 – Seal coat from Ralls County line to Route TT near Ashburn; scheduled to begin Aug. 13; estimated completion: Summer 2012
US 61 – Pavement repair and resurfacing north and southbound lanes from just north of Route OO to Route B; pavement repairs in progress; one lane traffic during working hours; estimated completion: July 2012
Maintenance
MO 79 – Aug. 6-8 one lane traffic 7:30 a.m. to 11 a.m. for pavement repairs at various locations 3 miles south of Louisiana
MO 79 – Aug. 6-8 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations from north of Louisiana to Route TT
Route C – Aug. 6 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations from US 61 to Route F in Ralls County
Route J – Aug. 6 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations from MO 161 to end of State Maintenance
Route OO – Aug. 7 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations from US 61 west to the end of State Maintenance at Lincoln Co. line
Route FF – Aug. 7 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations from US 61 west to end of State Maintenance
Route WW – Aug. 8 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations from US 61 east to Route D
Route TT – August 8 one lane traffic 7:30 a.m. to 4 p.m. for pavement repairs at various locations near Ashburn
Various Routes – Aug. 6-17 possible intermittent lane closures or slow moving vehicles blocking driving lane for surface and/or roadside maintenance operations in various locations.
Ralls County
Construction
MO 19 – Resurface from US 61 near New London to just north of Laddonia at Route J; scheduled to begin Aug. 6; cold milling operations for bonded concrete intersection at Rte. 19 & Rte. H/P in Center; estimated completion: Summer 2012.
Route T – Resurface from just south of MO 79 to Route N south of Hannibal; 92% complete; shoulders and striping remain; estimated completion: Summer 2012
MO 154 – Resurface from MO 19 to US 54 near Hutchison between Curryville and Vandalia; job not scheduled; estimated completion: Summer 2012
Route E – Seal coat from MO 79 to end of State maintenance near Saverton; scheduled to begin Aug. 13; estimated completion: Summer 2012
Route T – Seal coat from Route N south of Hannibal to MO 79 near Ashburn; scheduled to begin Aug. 13; estimated completion: Summer 2012
Route V – Seal coat from Ralls Street in New London to Route T; scheduled to begin Aug. 13; estimated completion: Summer 2012
Route N – Seal coat from Route T to MO 79 near Saverton; scheduled to begin Aug. 13; estimated completion: Summer 2012
Maintenance
Route 154 – Aug 6 one lane traffic 7 a.m. – 4:30 p.m. for pavement repairs at Spencer Creek Bridge
Route DD – Aug. 7 ROAD CLOSED 7 a.m. – 4 p.m. ¼ mile south of US 36 for culvert replacement
Route F – Aug. 6-9 one lane traffic 7 a.m. – 4:30 p.m. for ditching and culvert repairs from Rte. 154 to Rte. 19
Route 19 – Aug. 9 one lane traffic 7 a.m. – 4:30 p.m. for pavement repairs at Gallaher Creek Bridge just south of Route EE

Posted on Wednesday, August 8, 2012 at 8:50 am